Road works on Wybong Road are being completed and weather permitting the works should be complete by the end of June. During this time works to be completed will be:

Schedule of works for the period 01/08/2009 to 11/09/2009 (6 weeks)

Location Work Type Works
Spring Creek Bridge & Sandy Creek Bridge Bridge approach pavement works. Bridges approach to be sealed and concrete barriers and guard rail will be installed on each end of bridges by the end of August.
Castlerock Rd & Wybong Intersection Castlerock Rd Permanent Bus bay Earthworks and pavement works to be completed and re-opened to Public by end of August.
Approx. 1.5km From Bengalla Link Road towards to Sandy Hollow (before Sandy Creek Bridge) Box Culvert extension Both ends of box culverts to be extended approximately 3m, including new wing walls.
Approx 770m from Ridgelands Road towards to Sandy Hollow Culvert extension Approx. 3m either end of culverts to be extended with new wing walls.
Approx. 1.6km From Bengalla Link Road towards to Sandy Hollow Shoulder widening and Road Pavement Re-construction
  • Approx. 1.6km of Wybong Road will be reduced to one lane for shoulder widening and road pavement re-construction works in two stages (0.6km and 1km sections).
  • Road works will be a maximum of 1km in length at any one time.During section works traffic lights will be in place at each end of the section to control single traffic flow.
  • Upon completion of shoulder widening the entire road width will be sealed and opened for two-way traffic.A speed limit of 40km/per